Timeline
As with any project of this size, there will be some inconvenience, and perhaps even some chaos. But it will be exciting and the final project will be well worth the disruption with a beautiful new facility for us to be proud of and enjoy for many years to come.
| March – April 2004 |
Master Planning |
| May – June 2004 |
Concept Design |
| July – December 2004 |
Design Development & Construction Documents |
| January – February 2005 |
Bidding and Negotiation |
| April 2005 |
Start Construction – New Office Wings |
| June 2006 |
Relocate Information Technology to North Wing |
| July 2006 |
Demolish Annex & Services Building and Start Construction on New Commons Building |
| August 2006 |
Relocate Employees to North & South Wings. Renovate 1975 Building. |
| March 2007 |
Reoccupy 1975 Building. Renovate 1931 Building. |
| September 2007 |
Reoccupy 1931 Building |
| Fall 2007 |
Building Dedication Ceremony
|